Overview production/consumption:  8 day  6 week  12 month  3 year      Overview transmission:  8 day  6 week  12 month      Utilities:  Search   Advanced search   Enable Alerts


Failures and planned diverging trading capacity for Nordic Electricity Exchange Area interconnections during the next 8 days

Areas
Line
Normal
Trading
capacity MW
Updated: 2010-03-09 14:52:34 

= Line out or reduced at date.
Available
Trading
capacity MW
 Remarks
From To Export Import 09.03 10.03 11.03 12.03 13.03 14.03 15.03 16.03 Export Import
                               
DK1 DE Border between Denmark and Germany 1500  950  1100  950   01.03 - 09.04: Due to work on t ...
NO2 DK1 Skagerrak 950  1000  250  250   12.03 - 12.03: SK3 will be out ...
DK1 SE Konti Skan 740  680  370  340   16.10(2009) - 01.11: Due to failure o ...
EST FI Estlink 350  350  350   01.01 - 31.12: Estlink limitati ...
FI SE Finland-Sweden 1650  2050  1400  2050   08.03 - 12.03: Work at Rauma su ...
NO2 NL NorNed 700  700   29.01 - --.--: Due to a cable f ...
NO2 NO1 NO1-NO2 3000  2000  1700  1300   11.01 - --.--: As described in ...
NO3 NO4 NO3-NO4 600  600   11.01 - --.--: Norway split int ...
NO3 NO4 NO3-NO4 700  700   20.01 - --.--: To conform with ...
NO3 NO3 Central Norway  25.01 - --.--: Due to low inflo ...
NO4 SE NO4-SE 800  600  800  600   11.01 - --.--: Norway split int ...
NO3 SE NO3-SE 600  600  600  600   11.01 - --.--: Norway split int ...
NO1 NO1 ELSPOT  11.01 - --.--: From 11.01.10, N ...
NO1 SE NO1-SE 2050  2000  2000   11.01 - --.--: During high-load ...
NO4 SE NO4-SE 800  600  600  600   20.01 - --.--: To conform with ...
NO1 SE Hasle-Halden 2145  2095  650  850   08.03 - 12.03: Work in Halden s ...
NO3 NO4 Tunnsjĝdal-Namskogan 900  700   10.03 - 10.03: Required maintenance
NO1 NO2 ELSPOT  15.03 - --.--: Due to possible ...
NO2 NO1 ELSPOT 2600  1600  2600  1600   15.03 - --.--: from 15.03.2010: ...
NO5 NO2 ELSPOT 700  550  700  550   15.03 - --.--: From 15.03.2010: ...
NO1 NO5 ELSPOT 650  700  650  700   15.03 - --.--: Capacities refer ...
NO1 NO5 ELSPOT  15.03 - --.--: Installed produc ...
NO1 SE Halden-Skogsäter 2145  2095  850  650   16.03 - 18.03: Work in Halden s ...
NO3 SE Nea-Järpströmmen 600  600   22.06(2009) - 30.03: Construction of ...
NO4 SE Nea-Järpströmmen 800  600  600  450   22.06(2009) - 30.03: Construction of ...
SE PL SwePol Link 600  600  600   01.03 - 31.03: Svenska Kraftnät ...
SE SE Message from Svenska Kraftnät  29.11(2005) - --.--: During the high ...
SE SE System protection  25.03(2006) - --.--: A system protect ...
SE SE West Coast corridor  28.03(2006) - --.--: Due to high tran ...
SE NO1, DK1, DK2, SE, PL, DE West Coast corridor  19.04(2007) - 31.08: The maximum capa ...
SE SE Peak Load Reserve  16.11(2009) - 15.03: Information abou ...
SE SE GAS turbines  21.02 - --.--: E.ONs gas turbin ...
SE SE Finnböle  15.03 - 29.04: The reinforcemen ...